The 1996 Party Wall Act came into force throughout England and Wales on 1st July 1997. The purpose of the act is to enable the development process by granting rights to those wishing to develop land, not otherwise available at common law, in particular access to neighbouring land and the right to site scaffold and plant as reasonably necessary to enable the works. The flip side of this is that the rights of neighbours are much better protected under the Party Wall Act than would otherwise be the case. Of particular note is the strict requirement for the person carrying out the works to make good or pay for the making good of any damage caused to neighbouring property.
Three main types of work are covered by the Party Wall Act, which are:
- Works to a party wall or structure – examples of this might include the vertical extension of a party wall, for instance to enclose a new roof level extension or the cutting away of part of a wall, to accommodate a beam to be installed within it or to cut into the wall for flashings.
- Building up to or astride the boundary – examples of this might include the construction of an extension tight up to the boundary line, or the construction of a new party fence wall astride the boundary.
- Excavations within 3 meters/6 meters of neighbouring property – typically this is when an excavation is proposed to be constructed within 3 meters of a neighbouring building and a lower level than the footings of that building. A 6 meter notice is very similar but applied to buildings between 3 meters and 6 meters from neighbouring property and constructed with very deep foundations.
The Parties
The Party Wall Act identifies the parties as being:
- The Building Owner i.e. the person who has commissioned the works
- The Adjoining Owner i.e. the person who owns the neighbouring property.
In advance of works commencing, the Building Owner must serve notice on any Adjoining Owners likely to be affected by the work. Once received, the Adjoining Owner can either consent to the works, dissent but agree in the appointment of a single Party Wall Surveyor or dissent and appoint another Party Wall Surveyor. To see a typical form of notice click here.
If the Adjoining Owner fails to respond then the Surveyor appointed by the Building Owner can appoint a Surveyor on the Adjoining Owner’s behalf.
The Party Wall Act provides that in the event of one of the two Party Wall Surveyors failing to respond the remaining Surveyor can proceed on his own, this is known as acting Ex Parte.
The Award
The Party Wall Surveyors or the Agreed Surveyor then proceeds to draft a Party Wall Award which is a legal document defining the rights of the parties, what work is to be done, how the work is to be done and what will happen if damage occurs. The award will also detail which of the parties will pay the surveyors fees. To see an example of a Party Wall Award click here.
Depending upon the complexity of the work the surveyors or agreed surveyor will need to inspect the works as they progress so as to ensure that the likelihood of any damage to neighbouring property is minimised. Once the work is complete then a final inspection is usually made in order to sign off the work.
As regards costs, in almost all cases the Building Owner is responsible for the costs of the Party Wall Award including the fees of the Party Wall Surveyors or Agreed Surveyor.
It is important to factor in a reasonable time period to complete the Party Wall Award prior to commencement of work. Certain waiting times are built into the procedure to allow due consideration by the parties and the proper planning of the works. Whilst this can be shortcut by the agreement of the parties, this is no means guaranteed.
In general terms for work of simple content, 3 months is a reasonable period of time to allow for the completion of a Party Wall Award
Finally, should a Building Owner fail to serve a notice on an Adjoining Owner and proceeds with work, then an Adjoining Owner could apply for an injunction to halt the works whilst a notice is served and an Award agreed. This could prove extremely costly and inconvenient for the Building Owner. So for those planning to carry out the development of their property, it is vitally important that the advice of a Party Wall Surveyor is sought at the earliest opportunity and certainly well in advance of any planned start date.
Any questions you want answering? Either contact us using the form on the right or view on Party Wall Act FAQs.